Annual Street Rehabilitation and Preventive Maintenance Project

Summer 2018 - Annual Street Rehab Project Information

Public Works is bringing you fresh streets! Be on the lookout for contractor notices 3 days prior to the start of work this August 2018. Approximately one-third of all City streets will be slurry sealed or repaved to improve and maintain pavement quality. Normal construction impacts may include dust, noise, traffic delays and parking restrictions. Project notifications will also be available via the City’s Twitter (@EmeryvilleCA).

Schedule

Completed August 2018

  • August 21 - 24: Telfer Pavement Technologies, LLC finished palm tree removal and did necessary USA alerts for median removal work.

Completed September 2018

  • September 4 - 7: Telfer Pavement Technologies, LLC performed median removal work on Shellmound Street. Temporary paving/striping will remain until separate contractor (De Silva Gates) performs final paving efforts from curb to curb on Shellmound Street at end of September.
  • September 10 - 14: Telfer Pavement Technologies, LLC completed preliminary work needed in order to complete slurry seal work on streets throughout town (all red areas of map below).
    • Work included remaining pothole/digout repairs, crack seal/repair, and various other preliminary items before slurry seal is placed.
  • September 17 - 21: DeSilva Gates Construction began work on Shellmound Street from the 40th Street Bridge to Shellmound Way. 
    • Contractor adjusted and lowered manholes, gate valves and utilities in the roadway.
    • Contractor will do digout repairs for larger potholes or failed pavement areas. Most of these locations are near bus stops and near the median areas.
    • On Thursday, DeSilva Gates Construction will begin Grind and Pave work on Shellmound Street from the 40th Street Bridge to Shellmound Way. 
  • September 17 - 21: Telfer Pavement Technologies, LLC completed slurry seal work throughout City on all red areas on map below.
  • September 24 - 28: DeSilva Gates Construction completed Grind and Pave work on Shellmound Street from the 40th Street Bridge to Shellmound Way.
  • September 27 - 28, and 30th: DeSilva Gates completed night work on Christie Avenue and Powell Street.

Completed October 2018

  • October 1 - 5: DeSilva Gates finished Grind and Pave work on Christie Avenue and Powell Street.
  • October 1 - 5: Telfer Pavement Technologies, LLC finished sealer on City Civic Center Parking Lot.
  • October 8 - 19: DeSilva Gates completed adjustment of manholes/utilities on Shellmound Street.
  • October 8 - 31: Telfer Pavement Technologies, LLC completed striping work in slurry seal work areas throughout City.
  • October 22 - 31: DeSilva Gates started adjustment of manholes/utilities on Christie Avenue and Powell Street
  • October 15 - 31: DeSilva Gates completed striping work in all Grind/Pave work areas.

Tentative Schedule November 2018

  • DeSilva Gates to complete adjustment of manholes/utilities on Christie Avenue and Powell Street
  • DeSilva Gates to complete punch list striping and signage items on Shellmound Street, Christie Avenue, and Powell Street
  • Telfer Pavement Technologies, LLC to complete punch list striping and signage items on slurry seal work areas throughout City.
  • Both projects are expected to be complete before Thanksgiving

FlyerSeptember2018

Shellmound street