Public Works

Report a Problem: Engage Emeryville - SeeClickFix
Streetlight Repair Reporting: http://www.dcelectricgroup.com/street-light-repair.html

The following updates are for construction-related work being done within and/or impacting the public right-of-way.

The status of Capital Improvement Program (CIP) projects can be found here.

Construction Projects

Annual Street Rehab Project Starts August 2018

Public Works is bringing you fresh streets! Be on the lookout for contractor notices 3 days prior to the start of work this August 2018. Approximately one-third of all City streets will be slurry sealed or repaved to improve and maintain pavement quality.

The Construction Notification Flyer was mailed out the week of July 9, 2018. Normal construction impacts may include dust, noise, traffic delays and parking restrictions. Please visit this page for updates. Project notifications will also be available via the City’s Twitter (@EmeryvilleCA).

PG&E Natural Gas Pipeline Upgrade Projects


PG&E is upgrading pressure-regulating equipment on the natural gas pipelines in Emeryville as part of a system-wide safety program. Work has already begun and will continue through the end of 2018.

The Emeryville Municipal Code noise ordinance limits construction work to Monday through Friday, 7 AM to 6 PM. In addition, Public Works has limited work hours on the following streets to lessen impacts to traffic, but still provide time for PG&E to complete their projects quickly:

Christie Ave: 9 AM – 3:30 PM
Shellmound Way: 9 AM – 3:30 PM
Powell St: 9 AM – 3:30 PM
Hollis St: 7 AM – 4 PM

For questions on these PG&E projects, please contact the local PG&E representative:
Travis Neff, Outreach Specialist
415-973-3089
gasprojectinfo@pge.com
    

PG&E PM#30986349 - Christie Ave & 64th St

Location:

Christie Ave & 64th St Site Plan

Scope:

Notification Letter

Schedule:

 Project Schedule

Contractor:

Teichert Pipelines, Inc.
  

PG&E PM#31311278 - Beaudry St & Stanford Ave


Location:

 Beaudry St & Stanford Ave Site Plan

Scope:

Notification Letter

Schedule:

 Work began June 25, 2018 and will continue through August 2018.

Contractor:

 Henkels & McCoy, Inc.

PG&E PM#31308544 - San Pablo Ave & 45th St


Location:

 San Pablo Ave & 45th St Site Plan

Scope:

Notification Letter

Schedule:

 Work began June 14, 2018 and will continue through November 2018.

Contractor:

 Henkels & McCoy, Inc.
   

PG&E PM#31021606 - 43rd St & Adeline St


Location:

43rd St & Adeline St Site Plan

Scope:

 Update of natural gas distribution lines.

Schedule:

 Final restoration and striping is scheduled for completion in early July 2018.

Contractor:

 Restoration will be completed by AJW Construction.
   

PG&E PM#30986351 - Hollis St & Park Ave: COMPLETED


Location:

 Hollis St & Park Ave Site Plan

Scope:

Notification Letter

Schedule:

 Project Schedule

Contractor:

Teichert Pipelines, Inc. 


UPRR Maintenance Project


Union Pacific Railroad (UPRR) will be replacing more than 16,000 railroad ties between the cities of Emeryville and San Pablo. The tie installation project began on April 1st, 2018 with an anticipated completion date of May 23rd, 2018. This project is being done as part of the annual maintenance work across UPRR's network. Due to the commuter schedule in the area, the work can only be performed at night during a curfew from 9:30 p.m. to 5:30 a.m.

Please note that the City does not have any jurisdiction over Union Pacific Railroad and therefore City regulations such as the Noise Ordinance, which governs construction hours, and procedures for obtaining a waiver from the Noise Ordinance do not apply to UPRR projects. Impacts to residents may include bright lights, construction noise, and train horns.

UPRR states the following regarding this project: "Nothing is more important to Union Pacific than the safety of our employees, customers and the communities we serve; therefore, ensuring that our tracks and crossings are safe for trains to traverse through is a priority. We apologize for the inconvenience and noise impacts to local residents. Our engineers will work diligently to complete the project during its scheduled time frame." 

For more information, please contact: 

Francisco Castillo, UPRR Public Affairs Director
Phone (916) 200-6248
Email FCASTILLO@up.com
Twitter @fcastillo80



Horton Street Trial Traffic Calming Project


Location:

Horton Street between 45th and 53rd Streets link to site plan.

Benefit:

This project will construct temporary traffic calming measures and their effectiveness will be evaluated.

Scope:

 Install temporary speed bumps, signage and striping

Schedule:

Project is on-going.

Impact:

Parking and traffic will be impacted during working hours. 

Contractor:

 Chrisp Company website

City Project Manager:

 Michael Roberts, Senior Civil Engineer
Send feedback regarding the trial traffic calming project via this survey.
    

City Maintenance Work


Major maintenance projects will be posted here.

Public Works Responsibilities



The Public Works Department is responsible for designing, inspecting, and managing the City Capital Improvement Projects, including: 

  • City parks
  • Sidewalk and street construction / reconstruction
  • Street lights
  • Storm drains and sewer
  • Traffic signals
  • Water
Report a Problem: Engage Emeryville - SeeClickFix
Streetlight Repair Reporting: http://www.dcelectricgroup.com/street-light-repair.html