Partial Building Permits

Issuing Partial Building Permits
The Building Division may issue partial building permits other than foundation permits. Sometimes it is expedient to issue separate structural permits as well. If an applicant wishes to subdivide a building permit in this manner, the first permit application must be accompanied by a schedule of all planned submittals for the project. Additional fees will be required.

For more information, view the Guidelines for Partial Building Permits.

Limitations on Partial Building Permits
Partial permits for plumbing, electrical, and mechanical work will not be issued for a single project. Underground and site utilities shall be shown on foundation plans and shall be a part of that permit.